Define the project's outcomes
A project is work that produces one defined result: a website, a wedding shoot, a renovated kitchen. Operations is work that repeats: baking each morning, answering orders. Operations are run for steadiness and are covered under Operations management. A project is new each time, so most of its risk sits in what nobody has worked out yet.
Say you are a freelance designer in Klang. A kindergarten asks you for a website. That job is a project, and the kindergarten's principal is the stakeholder whose approval decides whether the job is finished.
Start with scoping
Scope is determining what the project will deliver, and by implication everything it will leave out. You write a scope statement: five pages, a contact form, photos and text supplied by the kindergarten, one round of design changes, one hour of training. Each item is a deliverable, a thing the client can see and accept.
Every project is held by the triple constraint: scope, time and cost. The three are tied together. More scope needs more time or more money. Less time needs less scope or more money. A client who asks for more at the same date and the same price is asking for one of the three to give way without saying which.
Break the scope into tasks
The work breakdown structure, splits it into tasks small enough to estimate and to tick off. Each task is given a dependency: the task that must finish before the next can start.
Estimates made from a single guess run short, because a guess pictures the day when nothing goes wrong. A three-point estimate takes the best case, the likely case and the worst case, and weights the likely case four times: (best + 4 × likely + worst) ÷ 6. For building the pages, your figures are 4, 5 and 12 days. The sum is (4 + 20 + 12) ÷ 6 = 6 days.
| Task | Working days | Starts after | Earliest days |
|---|---|---|---|
| A. Brief and sitemap | 2 | The start | 1 to 2 |
| B. Client gathers photos and text | 5 | A | 3 to 7 |
| C. Design the mock-up | 4 | A | 3 to 6 |
| D. Client approves the design | 2 | C | 7 to 8 |
| E. Build the pages | 6 | D | 9 to 14 |
| F. Add the content | 2 | B and E | 15 to 16 |
| G. Test and fix | 2 | F | 17 to 18 |
| H. Handover and training | 1 | G | 19 |
Laid out as bars against a calendar, this table is a Gantt chart: one row for each task, the length of the bar showing its duration, the position showing when it runs.
<show an example of a Gantt Chart>
The longest chain sets the end date
Two chains of tasks run through the project. A, C, D, E, F, G, H takes 2 + 4 + 2 + 6 + 2 + 2 + 1 = 19 days. A, B, F, G, H takes 2 + 5 + 2 + 2 + 1 = 12 days. The longest chain is the critical path, and its length is the shortest time the project can take: 19 working days. A day lost on any critical task is a day added to the end.
Task B is off the critical path. The content is needed on day 15 and can be ready on day 7, so the task has 7 days of float, also called slack: the delay a task can absorb before the end date moves. A principal who is a week late with photos costs nothing. A principal who takes 4 days to approve the design, against the 2 planned, moves the handover by 2 days.
Milestones are the points where something is finished and can be shown: design approved on day 8, pages built on day 14, site tested on day 18, handover on day 19. A milestone has no duration. It is either reached or it is not, which makes progress a fact.
Price the job from the plan
Duration is how long a task spans on the calendar. Effort is the working time it takes. Tasks B and D are the client's, so your own effort is 2 + 4 + 6 + 2 + 2 + 1 = 17 days.
| RM | |
|---|---|
| 17 days at your day rate of RM240 | 4,080 |
| Domain name, hosting and stock photos | 320 |
| Estimated cost | 4,400 |
| Contingency at 10% | 440 |
| Price quoted | 4,840 |
Contingency is an amount added for the things that will go wrong without anyone yet knowing which. You tie payment to the milestones: 40% on starting (RM1,936), 30% when the design is approved (RM1,452) and 30% at handover (RM1,452). How to present and defend the quote is covered under Sales and negotiation.
When the client asks for more
In the second week the principal asks for an online enrolment form that takes a deposit. The form is outside the scope statement. Additions that slip in without a change to time or cost are called scope creep, and they are the usual reason a fixed-price job ends at a loss.
The answer is change control: every request is written down as a change request, with what it adds to scope, time and cost, and the client decides. You estimate 3 more days of building. Building is on the critical path, so the handover moves from day 19 to day 22, and the price rises by 3 × RM240 = RM720 to RM5,560. The principal can accept, or keep the form for a later job. Both are good outcomes. The bad outcome is the one where you say "can" and build the form inside the original 19 days.
What could go wrong
A risk is something that may happen and would affect the project. Each is written in a risk register and rated on how likely it is and how much it would cost, then given a response decided in advance.
| Risk | Likelihood | Effect | Response |
|---|---|---|---|
| Client is late with photos and text | High | Low for the first 7 days of delay, because of the float | Ask for content on day 1, remind on day 5 |
| Client is slow to approve the design | Medium | High: on the critical path | Agree in writing that approval takes 2 working days |
| The contact form does not work with the hosting | Low | High | Test the form on the hosting during design |
Finish properly
A project needs a closing. The client confirms each deliverable against the scope statement, which is acceptance. Passwords and files are handed over, the final invoice goes out, and the job is declared finished, so that later requests become new work with a new price.
Then the plan is compared with what happened, a habit known as lessons learned. Suppose the build took 8 days against 6. Your effort was 19 days against 17, and the 2 extra days cost you RM480 against a contingency of RM440. Your next quote for a similar site starts from 8 days for the build.
Two pages of planning
If you work this way, you quote from a task list, so the price covers the work. The end date comes from the critical path, so the promise can be kept. Extra requests arrive as change requests with a price, so goodwill and profit both survive them. A scope statement, a task table, a risk table and a change note fit on two pages. At your first hire or first subcontractor, the same task table gains one column, the name of whoever owns each task.