Business Capacity
Say you cook sambal at home in Shah Alam and sell it in jars. You work 8 hours a day, 5 days a week. Each jar passes through three steps, and each step has its own capacity, the most it can turn out in a given time.
| Step | Rate | If it ran all 8 hours |
|---|---|---|
| Cook | One pot, 24 jars a batch, 2 hours a batch | 96 jars |
| Fill and seal | 60 jars an hour | 480 jars |
| Label and pack | 40 jars an hour | 320 jars |
The pot can cook 96 jars a day, or 480 a week. That is the design capacity: the output when nothing disturbs it. However, the pot must be washed and the ingredients prepared, so you actually did only 3 batches a day, not 4 batches. That gives 72 jars a day, or 360 a week, which is the effective capacity: the output a normal week allows.
Last month you made 270 jars a week. Two ratios say how well the capacity was used.
| Measure | Sum | Result |
|---|---|---|
| Utilisation: actual output as a share of design capacity | 270 ÷ 480 | 56% |
| Efficiency: actual output as a share of effective capacity | 270 ÷ 360 | 75% |
The first step: Effectiveness
Filling can handle 480 jars a day and packing 320, and the pot only makes 96 at most per day. The pot is the bottleneck, the step with the least capacity, and the whole business makes only what the bottleneck makes. This is the centre of the theory of constraints, set out by Eliyahu Goldratt in *The Goal*: find the constraint, get everything possible out of it, make every other step serve it, and only then spend money to enlarge it.
An hour lost at the pot is an hour of sales lost. An hour saved at the packing table changes nothing, because packing was already waiting for the pot. So you chop and weigh the next morning's ingredients the evening before, and the first batch starts the moment you do. A fourth batch fits in the day, and output can reach 96 jars with no new equipment.
A second pot would double cooking to 192 jars a day. Filling 192 jars takes 192 minutes and packing them takes 288 minutes. Together that is 480 minutes, a whole 8-hour day. The constraint would move from the pot to your own hands.
A bottleneck never disappears. It moves, and your job is to know where it sits now. For one person the last bottleneck is usually your own, which is why your first hire in operations should tackle your bottleneck.
The next step: Efficiency
Scheduling is deciding what is made when. Lead time is the time between an order coming in and the goods reaching the customer. You can make to stock, cooking ahead and selling from the shelf, which gives a short lead time and ties money up in jars that may not sell. Or you can make to order, cooking only what is asked for, which holds no stock and makes the customer wait.
A bazaar trader orders 120 jars for a Friday morning. Backward scheduling starts from the due date and counts back. At 72 jars a day, 120 jars need 2 cooking days, so the order must be on the stove by Wednesday morning. When several orders compete for the same days, the usual rule is earliest due date: the order due first is made first.
How many jars to keep
Inventory is everything held to make or sell: raw materials, work in progress (batches cooked and not yet packed) and finished goods. Too little stops production. Too much ties up cash and space.
You use 54 empty glass jars a day (270 ÷ 5). Your supplier takes 4 working days to deliver. If you order when the last jar is used, the pot stands idle for 4 days. The reorder point is the stock level at which a new order must be placed.
| Sum | Jars | |
|---|---|---|
| Used while waiting for delivery | 54 × 4 | 216 |
| Safety stock: extra held in case delivery is late or sales jump, here 2 days' use | 54 × 2 | 108 |
| Reorder point | 216 + 108 | 324 |
How many to order each time is a trade between two costs. Each order costs RM24 in delivery, whatever its size, so small frequent orders waste delivery charges. Holding a jar for a year costs about RM0.20 in space, breakage and money tied up, so large orders waste storage. The economic order quantity, or EOQ, is the order size where the two costs added together are lowest:
EOQ = √(2 × yearly demand × cost per order ÷ yearly holding cost per unit)
You use 13,500 jars a year (270 × 50 weeks). The sum is √(2 × 13,500 × 24 ÷ 0.20) = √3,240,000 = 1,800 jars.
| Order size | Orders a year | Delivery cost | Holding cost (average stock × RM0.20) | Total |
|---|---|---|---|---|
| 900 | 15 | RM360 | RM90 | RM450 |
| 1,800 | 7.5 | RM180 | RM180 | RM360 |
| 3,600 | 3.75 | RM90 | RM360 | RM450 |
Average stock is half the order size, because the stock runs from full to empty between deliveries. The formula assumes steady demand, unlimited storage space and no bulk discount, so EOQ is a starting figure to adjust. For you it means an order of about 1,800 jars roughly every 7 weeks.
Keeping every jar the same
Quality in operations means the product meets its specification, the written description of what a good unit is. Yours says 180 g of sambal, give or take 5 g, with a sealed lid. The allowed range is the tolerance.
Quality control is checking output against the specification. Checking every jar is slow, so you weigh 5 jars from each batch, which is sampling. A unit that fails is a defect. Last week 6 of 270 jars had loose seals, a defect rate of 2.2%. A loose seal found at the table costs one jar. Found by the customer, the same seal costs the jar, the postage, a replacement and perhaps a public review. This is why practitioners speak of quality at the source: check at the step where the fault is made. Finding and removing the cause of a defect is covered under Process improvement.
Depending on suppliers
Every input has a supplier, and each supplier is rated on the same few facts: price, lead time, minimum order quantity, quality of what arrives, and how often delivery is on time. Your jar supplier delivered on time on 8 of the last 10 orders, an on-time rate of 80%. That rate is why you hold 2 days of safety stock. A supplier at 100% would let you hold less.
Buying everything from one source is single sourcing. The price is usually better and the risk is higher: when that supplier runs out, production stops. A second supplier, tried with a small order before it is needed, costs little and keeps the pot running.
Running on figures
You now know the pot sets your limit at 96 jars a day, that a 120-jar order needs 2 days, that jars are ordered at 324 in lots of 1,800, and that 2.2% of seals fail. Each figure replaces a habit that costs money: taking an order the week cannot hold, running out of jars with a batch on the stove, buying a machine for a step that was never the constraint, or learning about a fault from a customer.